How I would plan a hardware refresh this year
Accelerators now age faster than the servers around them, and memory prices have jumped. I would put the two on separate refresh clocks and buy each on its own schedule.
I would stop refreshing servers and accelerators on the same schedule. They age at different rates now, and a plan that treats them as one purchase with one lifetime will be wrong about one of them.
The clearest public evidence comes from a company that buys more servers than almost anyone. Amazon's annual report for 2024 describes two changes in a row. Effective January 1, 2024, it lengthened the useful life of its servers from five years to six. Then, effective January 1, 2025, it shortened the useful life of a subset of its servers and networking equipment from six years back to five, and retired some equipment early. The reason it gave was "an increased pace of technology development, particularly in the area of artificial intelligence and machine learning."
Read those two changes together. Ordinary servers are lasting longer than they used to, and the equipment tied to AI is lasting less. An accounting department at a very large buyer has already split its fleet into two classes, and I would do the same in a refresh plan.
The supplier side says the same thing. In January, NVIDIA announced that its Rubin platform was in full production, with products from partners due in the second half of 2026, and described this as part of its "annual cadence of delivering a new generation of AI supercomputers." It also claimed up to 10 times lower inference cost per token than the generation before. That is a vendor's number and I would discount it. The schedule is the part to plan around. If you sign for accelerators this spring, their successor ships before your first year of depreciation is finished.
A general-purpose server does not work like that. A new CPU generation gives you more cores and somewhat better performance per watt, and a five-year-old host still runs most enterprise workloads perfectly well. Its refresh is usually forced by something outside the hardware: the support contract ends, the firmware stops getting updates, or the software on it reaches end of support.
Ordinary servers are lasting longer than they used to
A five-year-old host still runs most enterprise workloads
Refresh is usually forced by a support or software end date
Equipment tied to AI is lasting less
A new generation arrives on an annual cadence
A successor can ship within the first year of depreciation
Amazon lengthened server life from five years to six in 2024, then cut a subset back to five in 2025, citing the pace of AI development.
This year has two extra factors on the general-purpose side, and they pull in opposite directions.
The first is memory. TrendForce's forecast of February 2 put first-quarter contract prices for server DRAM up by around 90% over the previous quarter, which it called the largest quarterly rise on record, and enterprise SSD prices up 53% to 58%. It blamed AI and datacenter demand for the shortage. Those are an analyst's forecasts and they will move, but any quote you receive this spring has that in it. A like-for-like server refresh costs noticeably more than it did last year, and most of the difference is memory and flash.
The second is the calendar. Windows Server 2016 reaches the end of extended support on January 12, 2027, according to Microsoft's lifecycle page. Some of the hosts still running it were bought for it. The Secure Boot certificate work I wrote about in January also depends on firmware updates, and a model that has gone out of support may not receive one. So some servers have to go this year whatever memory costs.
Here is how I would put the plan together.
Start by sorting the general-purpose fleet into what is forced and what is habit. Forced means the operating system, the firmware or the hardware support has an end date inside the next eighteen months and no acceptable extension. Refresh those. Everything else is a candidate for another year of service, provided the vendor will still support it and you have spares. With memory where it is, a healthy four-year-old host is worth more than usual, and I would ask for extended support pricing before I asked for a replacement quote.
For what you do buy, size memory from measurement. Pull actual memory use from the hosts being replaced. The habit of doubling memory at every refresh was cheap insurance when memory was cheap, and at this spring's prices it is a real line in the budget. Check with your hardware vendor how long each quote is valid, because I would expect validity periods to be short this year.
Then treat accelerators as their own asset class with their own clock.
Keep them in dedicated nodes. If GPUs are spread across your general-purpose hosts, you cannot replace the GPUs without disturbing everything else, and you cannot extend the hosts without keeping the GPUs. Put them in servers bought for the purpose, so each kind can leave on its own date.
Buy in smaller tranches, more often. One large purchase locks the whole fleet to one generation on the day it starts aging. Two or three smaller purchases spread over the same period cost more in procurement effort and leave you with a mixed fleet. In return, part of your capacity is always recent, and each purchase is sized with real usage data from the one before.
Do not assume the chassis outlives the cards. Each accelerator generation has brought different power and cooling requirements, and the densest systems are now liquid cooled. Ask the server vendor, in writing, whether the chassis you are buying will accept the next generation. If the answer is no or "we cannot say," plan to replace the whole node and cost it that way.
Plan the second job before you buy. An accelerator that is too slow for your most demanding workload after two years can still do useful work: batch jobs, development and test, embedding generation, smaller models. Decide in advance where each tranche moves when the next one arrives. That cascade is what lets you depreciate over a sensible period even though the front-line life is short.
Rent the uncertain part. If you do not yet know how much inference demand you will have in a year, buy for the load you can measure today and use cloud capacity for the rest until the pattern is clear. Owning idle accelerators through a generation change is the most expensive outcome on this list.
Ask finance for a separate depreciation schedule. If accelerators sit on the same five- or six-year schedule as everything else, the books will say they are worth keeping long after the engineers have stopped wanting to use them, and replacing them will look like a write-off. A shorter schedule for that class makes the refresh a planned event.
The ownership lines are worth stating, because each of these clocks has a different owner. The hardware vendor owns the support dates and the answer about chassis compatibility. The software vendor owns the end-of-support date. Finance owns the depreciation schedule. The platform team owns the two refresh calendars and the cascade. The application teams own the demand forecast for accelerators, and if they cannot give one, that is a reason to rent.
One caveat. All of this assumes you have accelerators to plan for. Many organizations do not yet, and for them this year's refresh is a memory-price problem and an end-of-support problem. The same sorting into forced and healthy applies, and so does sizing memory from measurement.
The first thing I would do this week is list every host with its purchase date, its support end date and the end-of-support date of what runs on it, then mark which column forces the refresh. Most fleets have never had that list in one place. Once you have it, the two classes of equipment and their two schedules are easy to see.
Sources
Views are my own.