Liquid cooling is reaching racks that were never built for it

Dense AI hardware is bringing liquid cooling into ordinary enterprise rooms and colocation cages. What a facility designed around air is missing, and who owns the coolant loop once it is installed.

If a liquid-cooled rack is on your order list this year, hold the first planning meeting with the facilities team, and hold it before the purchase order goes out. The server arrives on a truck. Everything it needs gets built into the room, and most enterprise rooms were built around air.

For years liquid cooling belonged to supercomputing sites and a handful of very large operators. Dense AI hardware has widened that. Uptime Institute's July 2025 data report on direct liquid cooling says adoption "remains gradual, with most operators still relying on traditional air cooling methods." That describes the average operator. The infrastructure team that has been told to put two GPU racks into an ordinary enterprise datacenter or a colocation cage by the fall is in a different position, because that team gets no gradual transition.

ASHRAE's Technical Committee 9.9 warned about this in a 2021 white paper on liquid cooling in mainstream datacenters. "Server manufacturers will stretch air cooling as far as possible," it says, "but that has implications." One of them is fan power, which the paper puts at 10% to 20% of server power for some of the denser servers. Eventually the fans cannot move enough air through the chassis, and the chip maker specifies liquid.

How the heat leaves the rack

Most of what is sold for AI today uses direct-to-chip cooling. A metal cold plate sits on each processor and GPU. Coolant flows through the plate, picks up the heat and leaves through manifolds at the back of the rack. NVIDIA's documentation for its DGX GB200 rack describes compute trays "cooled by liquid that runs up and down the rack through manifolds."

The coolant inside the rack is a closed loop. A coolant distribution unit (CDU) pumps it and passes its heat through a heat exchanger to the building's water, so facility water never runs through the servers. That gives you two loops to design, fill and maintain, and the CDU is where they meet.

Two details catch people out.

A liquid-cooled rack still heats the room. In that same NVIDIA rack the networking and storage components are air cooled, with fans. ASHRAE's paper says it plainly: "Even at a small scale, a fully populated liquid-cooled rack could generate significant heat into the data center." Your air handlers keep working after the pipes go in.

The water temperature is a specification, and equipment is rated against it. ASHRAE classifies facility water by its upper temperature limit in degrees Celsius: W17, W27, W32, W40, W45 and W+. Equipment rated W32 expects facility water at or below 32°C. The white paper expects the temperatures that hardware will accept to fall as chips draw more power, and it tells facilities to plan for that. If your building's efficiency case rests on warm water and few chiller hours, read that section twice.

Which equipment accepts your facility water
30°C
W17W27W32W40W4530°C

Equipment rated W32, W40 or W45 accepts water at 30°C. Equipment rated W17 or W27 needs colder water.

The class number is the upper limit for facility water in degrees Celsius.

What a room built for air is missing

Water at the row. Many rooms have chilled water at the perimeter, feeding the air handlers, and none near the racks. Bringing it to the rack means new piping above or below live equipment. ASHRAE's guidance for overhead runs is to keep piping above the aisles and, where connections pass over critical equipment, to install "drip pans with leak detection and piped drains routed to the floor."

If you cannot get facility water to the rack, there is a bridge. A liquid-to-air heat exchanger in the rack or the row cools the coolant loop and blows the heat into the room. ASHRAE describes this as an interim arrangement and a less efficient one. It also means the room's air system has to absorb the full heat of the rack, so check that it can.

Floor strength. A rack full of cold plates, manifolds, coolant and power shelves can weigh far more than the rack your floor was specified for. The figure varies by system, so ask the vendor for the filled weight of the rack and of the CDU. Then check the route as well as the destination. ASHRAE's paper says load paths for heavy racks need the right rating for rolling loads, and it lists "elevators, ramps, thresholds, corridors." It also notes that some older datacenters moving to denser racks end up with more empty space than you would expect, simply because of floor loading limits.

Permission. If you are a colocation tenant, read the contract. ASHRAE observes that colocation service level agreements "may be specifically written to exclude water close to the racks."

Water chemistry. A closed loop stays healthy only if everything the coolant touches is compatible with it. The paper recommends creating a wetted materials list during design and keeping it current, and planning how the loop will be cleaned and flushed before it is filled. In its words, "A closed system's long-term success often is determined in the design and installation phase."

Who owns the loop

In an air-cooled room the ownership line was easy to draw. Facilities delivered cold air to the front of the rack, and IT owned everything inside it. A coolant loop crosses that line.

The facility water side is the facilities team's problem. The servers are IT's problem. The specification is the hardware vendor's problem: water class, flow rate, pressure, coolant type and approved materials all come from the vendor, so check with your hardware vendor and get the numbers in writing.

The CDU, the manifolds and the coolant between them sit in the middle, and in most organizations nobody has owned anything like them before. Settle these on paper before installation:

  • Who monitors coolant quality, and how often.
  • Who receives a leak alarm, and what the alarm does by itself. NVIDIA's rack documentation lists leak detection as part of the system. Somebody still has to decide whether an alarm pages a person, closes a valve or powers down a tray.
  • Who is allowed to shut off flow to a rack, and who has to be told first.
  • Who holds the service contract for the CDU, and what happens to the racks behind it while it is being serviced.

Service procedures change too. Replacing a failed node used to mean sliding it out. Now the coolant lines come off first. The couplings are made for that, but the technician needs a written procedure, the training to follow it and something to catch what drips. Find out whether your own staff will be allowed to do this work or whether the vendor requires its own engineers, because that decides how long a failed node stays failed.

What I would ask before ordering

Most of this can be settled with one list of questions, sent to the hardware vendor and to your facilities team (or your colocation provider) at the same time.

  • What water class and flow does the rack need, and can the building supply it on the hottest day of the year?
  • How much of the rack's heat still goes into the room air?
  • What do the rack and the CDU weigh when filled, and is every floor between the loading dock and the final position rated for that?
  • Who supplies, installs and commissions the CDU and the piping?
  • What happens to the rack if coolant flow stops, and how quickly?
  • Does the contract for the space allow liquid at the rack?

Uptime's report found that operators are most likely to judge a liquid cooling system on how readily it integrates into existing infrastructure. I would weigh it the same way. The answers to those six questions matter more to the project than anything on the server's data sheet.

One caveat. Most enterprise workloads still run comfortably on air, and an ordinary hall does not need pipes on account of two GPU racks somewhere else. The planning change is narrower than that. ASHRAE's paper recommended in 2021 that any future datacenter include the capability to add liquid cooling in its design. If you are building, renovating or renewing a lease this year, ask what it would cost to leave room for the piping and a CDU now, while the ceiling is open.